Phase One Construction

The Roy Blunt Luminary Park is a sustainable urban park and public green space over interstate 670 (I-670) in downtown Kansas City, Mo. Phase One of construction begins late 2026, and requires closures of city streets and I-670.

I-670 and City Street Closure Information

Closures are currently expected to begin December 2, 2026. I-670 is scheduled to remain closed through September 2028, while intermittent city street closures will continue until Phase One construction is expected to be complete in spring 2029.

I-670 Closure

  • The project will close both directions of I-670 from Interstate 35 to U.S. 71. 
  • I-670 is scheduled to close early December 2, 2026, through September 2028.

City Street Closures

  • The project will close eastbound and westbound Truman Road from Broadway Boulevard to Baltimore Avenue.
  • Intermittent street closures and lane reductions are scheduled periodically as work progresses to facilitate construction. 
  • Partial street and lane closures impacting eastbound and westbound Truman Road, Wyandotte Street, and Baltimore Avenue are scheduled to continue through spring 2029.

Subscribe for News and Notices

Sign up for email updates to get construction notifications, detour maps, and project news.

Improve I-70 KC

KCMO’s Luminary Park and MoDOT’s Improve I-70 KC project are separate projects. Click the button for Improve I-70 KC closure dates and details.

Fact Sheet

Luminary Park Phase One Construction Detour map

Closure Map

Luminary Park: Phase One construction closure map for I-670 and city streets starting December 2026

Click I-670 and city street closure map image for larger view.

Detour Map

Luminary Park Phase One Construction Detour map

Click detour map image for larger view.

Frequently Asked Questions

When do the closures begin and how long will they last?

Both directions of I-670 from Interstate 35 to U.S. 71., and both eastbound and westbound Truman Road from Broadway Boulevard to Baltimore Avenue will close from December 2, 2026, through September 2028. 

Partial street and lane closures impacting eastbound and westbound Truman Road, Wyandotte Street, and Baltimore Avenue are scheduled to continue through spring 2029.

Why does this require a full closure of I-670?

Covering I-670 between Broadway Boulevard and Baltimore Avenue turns that stretch of highway into a tunnel. Crews will replace the pavement and drainage, build the structure overhead and install the tunnel’s life safety systems. That work spans every lane at once, so it can’t be done one lane at a time, and a full closure keeps both drivers and crews safe. The tunnel’s lighting, fire protection and monitoring systems must be installed, tested and working before this section of I-670 reopens to traffic.

What is being built during this phase of work?

Phase One builds approximately 50 percent of the tunnel along I-670 and constructs the first block of the park from Wyandotte Street to Baltimore Avenue near the Convention Center. Work includes:

  • Tunnel Infrastructure: Full construction of three blocks of supporting tunnel fire protection, emergency and safety systems infrastructure, from Broadway Boulevard to Baltimore Avenue.
  • Block One of the Park: Completion of Block One, from Wyandotte Street to Baltimore Avenue near the Convention Center.
  • Tunnel Systems Building: A building that houses fire protection, safety and operations equipment to support the entire project footprint, from Broadway Boulevard to Grand Boulevard.
  • Roadway and Infrastructure Work: Six blocks of new pavement and drainage improvements on I-670, from Broadway Boulevard to Grand Boulevard.
What will Block One feature?

Block One features and activation amenities include, but are not limited to:

  • Walking paths, terraces, and picnic areas
  • Nature and woodland spaces
  • Swings, slides, boulder crawls, and adventure play areas
  • Art installations and performance areas
  • Space for food trucks and community events
  • Lighting, security, and public safety features
    How do I get around the closures?

    Traffic impacts vary depending on the originating direction. Businesses in the area will remain open and accessible by marked detours. City street and interstate closures and detours will be marked with signage. Drivers are encouraged to find alternate routes for their destination to navigate around the I-670 closure. Due to the project area size, there is not a single detour route that works for everyone. Please see traffic maps or consult navigation apps for the best routes. 

    How does this closure relate to the I-70 closure?

    They are not related. KCMO’s Luminary Park and MoDOT’s Improve I-70 KC project are two separate projects. The Improve I-70 KC project will close I-70 from The Paseo Blvd. east to Van Brunt Blvd. and is scheduled to close early January 2027 through December 2027. For details on the Improve I-70 KC closure, visit http://modot.org/i-70-closure-2027.

    Will construction affect nearby businesses?

    Every business in the area will stay open, and marked detours will lead customers to them. If work blocks a business’s entrance or driveway, the project team will coordinate with that business first to keep the disruption as small as possible.

    Will construction noise be disruptive to the area?

    Construction noise isn’t expected to exceed the existing noise generated by traffic on I-670. With traffic removed from this section of the interstate during construction, the surrounding area may be quieter at night. Once I-670 reopens in September 2028, the park and tunnel structure are expected to help reduce traffic noise in the area.

    Who is on the project team?

    The project partners are the city of Kansas City, Mo., Downtown Council of Kansas City, and Port KC. The Construction Management/General Contractor (CM/GC) is a joint venture between Clarkson Construction and JE Dunn Construction. Rounding out the project team are HNTB, BNIM, OJB Studios (now part of Populous), Parson + Associates, and many other subcontractors.